Level — Successfully we move to the purpose!

21 / 10 At the moment, we are continuing to work on concreting of walls and structures: at the 4th floor of the ground part of the third building, at the 3rd floor of the second building, continuing the zero cycle works of walls concreting, floors, stairs and columns, at -2nd floor of the first building. Works on construction of walls of storerooms are conducted at the -1 th floor. Builders has started a gas boiler room construction.You can see the construction dynamics on our website. We have posted monthly photos in the section of the Apartments for your convenience — icon in the right top corner. Results of February already on the website!

You can get acquainted closer with the project and walk on Level Barvikha Residence just having called to our office! Our Sales managers will answer all your questions!